NCCS Discover Cluster
Timeline
- The following outlines the major events that will occur over the next 4 months. If users are interested in pioneer user access (early access) to the cluster, please contact user services. In addition, if users require assistance in porting their applications to the cluster environment, please contact user services.
- October
- Final integration tasks completed
- Early access and pioneer users
- November
- General user access
- Acceptance testing
- Migration of user applications
- December
- Base unit officially accepted
- Begin process of installing next scalable unit
- Migration of user applications continues
- January
- Scalable unit deployed for production
- Begin decommission of HP system
|
|
|
 |
|
|
|
 |